Once a soil erosion permit has been issued, site maintenance inspections are performed until projects are permanently stabilized and a Certificate of Completion has been granted by the Soil Erosion and Sedimentation Control Program.
Site Inspection Schedule
Permit Type
Description
Residential Permits
At minimum inspection will occur on a bimonthly basis, throughout the duration of the permit.
Residential Permit are valid for 18 months from the date of issuance, extensions are available
Commercial Permits
At minimum Inspections will occur on a monthly basis, throughout the duration of the permit.
Commercial Permits are valid for 24 months from the date of issuance, extensions are available
At a minimum, the Program will conduct inspections as mentioned above. The site inspection schedule does not include transfer inspections, re-inspections, final inspections or enforcement.