Projects

Drain Construction Projects

Under the Michigan Drain Code, the County Water Resources Commissioner can spend up to $5,000 per mile of drain on maintenance and repairs to a county designated drain. Any necessary repairs costing more than this allowable amount requires a drain petition, township resolution, or emergency situation. 

Project Status

Municipality
Project / Drain Name
Project Start Date
Anticipated Finish Date
Status
Contact
Augusta Township
Talladay Road (PDF)

Map (JPG)

06/06/2017
06/30/2019
Procuring easements

Scott Miller
Email Scott Miller
Phone: 734-222-6818

Bridgewater, Freedom & Saline TownshipsBridgewater Village Tile

Map (PDF)
03/29/2018
04/1/2020
Seeking bids fall 2019
Scott Miller
Email Scott Miller
Phone: 734-222-6818
City of Ann ArborHuron River Green Infrastructure Tree Planting 5504-0702/02/2018
06/30/2019
Under construction
Harry Sheehan
Email Harry Sheehan
Phone: 734-222-6851
City of Ann Arbor
Huron River Green Infrastructure Tree Planting 5504-08
03/11/2019
12/31/2020
Bids accepted
Harry Sheehan
Email Harry Sheehan
Phone: 734-222-6851
City of Ann ArborMillers Creek AA Pepper Pike 5626.0101/07/2019
11/30/2020
Bids accepted
Harry Sheehan
Email Harry Sheehan
Phone: 734-222-6851
Saline Township

Cammett & Luckhardt

Map (PDF)

03/01/2018
04/01/2019
Construction complete
Scott Miller
Email Scott Miller
Phone: 734-222-6818
Average time per project phase may vary depending on easement acquisition, appeals filed, MDEQ permit or other extenuating circumstances.